The standard in plain English

A criterion is one check. There are 20 in this standard. The free review runs the 13 checks that need only the RAMS document. The rest need your project requirements and site rules.

Each check has a weight: how much it counts towards the score. A gap is marked critical, major or minor to show how serious it is. Serious gaps set an upper limit on the score, called a cap.

Use the findings to ask for missing details or changes. The score does not approve the RAMS or give permission to start work. The full rules, calculations and legal references are below.

When a document can’t be read

If the review cannot read or assess the document, it gives no score. An unreadable document is not given a score of zero. Try a PDF where you can select the text, or a Word document. For a scan, use text recognition (OCR) before uploading it again.

Version 2.1.0, 7 October 2026. First effective 30 July 2026 as v1.0.0. Published by PlanOps. Licensed under CC BY 4.0: use it, print it, adapt it, with attribution. The argument for the standard is in What a competent RAMS review actually tests.


What this is

A published, versioned standard for reviewing a subcontractor's risk assessment and method statement (RAMS) against the requirement the principal contractor issued for the activity. It defines twenty tests in four parts, the weight of each, the legal or project basis each one supports, and an arithmetic method that turns the reviewer's verdicts into a 0 to 100 score where every point lost is traceable to a named criterion.

It is written so that a health and safety manager can adopt it on paper without any software. It also describes the review framework used by PlanOps. This edition clarifies the published guidance; it does not announce a new machine-rubric release. An automated result must identify the rubric and evidence scope used for that run.

Version 2 makes the review proportionate to the risk of the work. A carpet fitter and a steel erector are still read against the same twenty tests, at the same weights, into the same bands. What changes is that a test the activity does not engage is recorded as does not apply, with the reason written down, rather than marked as a failure. Eight tests always apply, whatever the trade. The rules for the rest are under "Which tests apply" below, and the reasoning under "Why proportionate is the standard".

It is not a British Standard and it is not a legal opinion. Passing a test here is evidence towards managing a duty or requirement, not proof that the duty has been discharged.

The statutory references in this edition are mainly for construction work in Great Britain. References to Building Regulations Part 2A apply to building work in England. Wales has Part 2B duties and competence requirements effective from 1 July 2026; check the applicable regime and transitional arrangements. Building-regulations competence concerns compliance of building work and is distinct from construction workplace safety under CDM. Different legislation applies in Northern Ireland.

How to use it on paper

The working checklist fits on two sides of A4: download the two-page checklist (PDF), print it, and put it next to the submission.

  1. Have the requirement you issued for the activity to hand: the risk category, the legislation you cited, any permit, any temporary works reference, the activity description, the risk level, and your organisation's own rules if any.
  2. Write down the hazard profile of the work: each hazard category it involves and how serious it is. Take it from the requirement where you recorded one. Where you did not, rate it yourself from the work described, and never from the submission's own rating (see "Which tests apply" below).
  3. Decide which tests apply before you mark any of them. Eight always do. For each of the others, ask whether this activity engages it. Where it does not, record does not apply and one sentence saying why. Where it does, the test applies, and a RAMS that is silent on it has not met it.
  4. For every test that applies, record a verdict: met, partially met or not met. Every criterion must carry either a verdict or a reasoned does not apply.
  5. For each criterion that is partially met or not met, record a severity, judged as the consequence if this work, with these hazards, proceeds as written: critical, major or minor. Critical means work under this RAMS could kill or seriously injure someone (no rescue plan, no temporary works design). Major means a material gap that must be closed before work starts. Minor means a limited deficiency that would not, on its own, materially affect safe execution.
  6. Score it using the method below, or simply apply the caps: any critical not met, serious gaps, send it back; any critical partially met, significant gaps; any major finding, at best gaps to close.
  7. Return the verdicts to the subcontractor with the review, including the reason for every test you marked as does not apply. The list of what was tested, and of what was not and why, is the review.

The four parts and twenty criteria

Weights sum to 100. The "evidence basis" column is a guide to why the criterion matters. It may name a direct legal duty, recognised guidance or good practice, or a project or contract requirement. It should not be read as saying the law requires that exact RAMS heading or wording. Abbreviations: MHSWR is the Management of Health and Safety at Work Regulations 1999; CDM is the Construction (Design and Management) Regulations 2015; HSWA is the Health and Safety at Work etc. Act 1974; Part 2A is Part 2A of the Building Regulations 2010 (England, competence, from 1 October 2023).

Part 1: Is the risk assessment real? (18 points)

#CriterionThe testWeightEvidence basis
1Method statement supported by risk assessmentEvery safety-significant method statement step rests on an assessed risk, and the risk assessment and method statement clearly connect to each other rather than sit side by side.9MHSWR reg 3; CDM reg 15(2); HSE guidance on using method statements to put risk assessments into practice
2Foreseeable hazards and controls for this trade, this activity and this siteThe risk assessment covers the hazards this activity actually presents on this site, with controls that follow the hierarchy of control.9MHSWR regs 3 and 4 and Schedule 1; CDM regs 13 and 15 where applicable

Part 2: Does the method statement say enough? (56 points)

Each criterion asks the same shape of question: is this section present, specific and adequate?

#CriterionThe testWeightEvidence basis
3Scope of works stated and specificThe method statement states its scope (locations, boundaries, exclusions, interfaces) specifically enough for the remaining criteria to be audited against it. Tests presence and specificity only; whether the scope matches the activity you asked for is criterion 18.5Supports CDM reg 15(2) planning and management: the work has to be clear before it can be planned
4ProgrammeDuration, sequence and working hours are stated well enough to judge the controls against them.3CDM reg 13(2) sequencing and time allowed; CDM reg 12 construction phase plan; CDM reg 15(4) where there is only one contractor
5Resources, competence and equipmentPeople, plant and equipment are named, with competence requirements and supporting evidence (cards, tickets, certificates) where applicable.5CDM regs 8 and 15(7); PUWER regs 4 and 9 where work equipment is used; Part 2A regs 11E and 11F where building work in England is in scope
6Hazard identificationHazards are task-specific rather than generic, with competent input where needed and review or authorisation under the contractor's own arrangements.7MHSWR regs 3, 5 and 7
7Control measuresControls follow the hierarchy: elimination or substitution where practicable, engineering and collective protection, supported by workable supervision, permits, inspections, briefings and suitable PPE.8MHSWR regs 4 and 5 and Schedule 1; CDM regs 15(2) and 15(8); Personal Protective Equipment at Work Regulations 1992 as amended
8Emergency arrangementsRescue, first aid, welfare and raising-the-alarm arrangements are specific to this activity and location.7CDM regs 30 and 31; MHSWR reg 8; Health and Safety (First-Aid) Regulations 1981; CDM Schedule 2 welfare; activity-specific rescue duties where applicable
9Temporary worksTemporary works coordination, design, checks and lifting responsibilities are addressed where the activity involves them. Judged on the work described, not only on what the requirement referenced (that is criterion 17).6CDM reg 19; BS 5975-1:2024 as recognised temporary works management practice; BS 5975-2:2024 where falsework is relevant; LOLER 1998 where lifting
10Interface with others and the publicSegregation, signage, security, dust and noise controls address who else is affected.5CDM regs 13(1) and 13(3) coordination; CDM regs 17 and 18; HSWA s3; COSHH, noise and environmental duties where those risks are present
11Training and informationInduction, task briefing, specialist training and card requirements are stated where applicable.4CDM regs 13(4), 15(8) and 15(9); MHSWR reg 13; Part 2A reg 11F for building work in England; site or scheme card rules where applicable
12Environmental issuesWaste, pollution prevention, noise, permits and monitoring are addressed where the activity or project requires them.3Project and environmental requirements; Environmental Protection Act 1990 s34 for waste; Control of Pollution Act 1974 ss60-61 where construction-noise controls or consents apply; environmental permits and site consents where applicable
13Monitoring and reviewChecking, enforcement, change management and briefing records are described.3CDM reg 15(2) "monitor"; MHSWR reg 3(3) review of assessment; briefing records as evidence of management

Part 3: Does it answer the requirement you issued? (22 points)

Each criterion compares the submission against the requirement for this activity.

#CriterionThe testWeightEvidence basis
14Addresses the risk category on your requirementThe submission engages the specific hazard category your requirement identifies.4Supports the principal contractor's CDM reg 13 planning and coordination duties; this standard uses the issued risk category as the comparison point
15Addresses the legislation cited on your requirementFor each piece of legislation or guidance named on the requirement, the relevant requirements are addressed in the method and controls.4Applicable duties under the legislation or guidance identified on the requirement, for example LOLER 1998, Work at Height Regs 2005, CAR 2012, COSHH 2002 or Electricity at Work Regs 1989
16References the permit process you requireWhere the requirement calls for a permit, the submission references raising and closing it.3CDM regs 12 and 15(3) where the permit forms part of the construction phase plan, site rules or a principal contractor or principal designer direction; otherwise a project or site requirement
17Addresses the temporary works you referencedWhere the requirement references temporary works, their design, inspection and coordination are addressed.3CDM reg 19; BS 5975-1:2024 as recognised temporary works management practice; BS 5975-2:2024 where falsework is relevant
18Scope matches the activity on your requirementThe submitted scope neither falls short of nor overruns the activity the requirement describes. Tests conformity only; whether a scope is stated specifically enough to audit at all is criterion 3.4Supports CDM reg 13 coordination by checking that this is the right RAMS for the right work
19Controls proportionate to the riskControls are proportionate to the actual foreseeable risk, taking account of the risk level recorded on the requirement.4MHSWR reg 3 suitable and sufficient assessment; CDM reg 15(2) planning and management; the requirement's risk level is used as review evidence, not as a substitute for the contractor's own assessment

Part 4: Does it meet your own rules? (4 points)

#CriterionThe testWeightEvidence basis
20Organisation requirementsGaps against your organisation's own requirements (client standards, framework conditions, site rules beyond the regulations). Does not apply when none were issued.4CDM regs 13(3) and 15(3) where the requirement is in the construction phase plan, site rules or a principal contractor or principal designer direction; other client, framework or company rules are project or contract requirements

Two conduct rules apply to Part 4 and are not scored: cite each organisation requirement by its exact reference when it is used as a test; and where no organisation requirements were issued, do not invent any, mark criterion 20 as does not apply.

Practical checks within the criteria

These examples explain the existing hazard, control and emergency criteria. Apply them where the activity presents the hazard; they are not extra scored criteria.

  • People and actions: identify who may be harmed and how, existing controls, further actions, who will implement them and by when. HSE's assessment guidance sets out these questions. Record action owners and deadlines for outstanding actions; do not invent a statutory requirement for a particular table layout.
  • Residual risk: where a numerical rating is used, check that the stated reduction is supported by specific, workable controls. PPE and competence may contribute, but mentioning either does not by itself justify a low score. Assess the suitability and effectiveness of the measures for the hazard.
  • Work at height: follow avoidance, fall prevention and mitigation, considering collective protection before personal protection. Where fall arrest is used, check suitable rescue arrangements.
  • Electrical work: check dead working and safe isolation, including preventing re-energisation and proving dead. A live-work proposal needs a specific justification against the applicable legal conditions and precautions; a competent electrician alone is not the justification.
  • Confined spaces: consider avoiding entry first. If entry is necessary, check the safe system and effective rescue arrangements. Reliance on emergency services alone is insufficient.
  • Hazardous substances: check task-specific exposure assessment and controls. A safety data sheet is an input to a COSHH assessment, not its replacement. Apply the separate asbestos and lead requirements where those hazards are present.

Supporting evidence and the reviewer decision

A reference to another document is not evidence that its contents were assessed. Record the review's evidence scope separately from whether a criterion applies.

Evidence statusWhat the review should record
Supplied and assessedThe document, revision and findings it supports.
Referenced but not suppliedThe reference and the affected conclusion that could not be verified. This does not prove that the arrangement does not exist.
Supplied but unreadableThe file and reading limitation, separately from a missing reference. Do not imply its contents were assessed.
Checked separately by the reviewerThe document and revision, where it is held, who checked it and how it resolves the finding.
Not applicable to the workThe activity-specific reason for excluding the criterion. Missing evidence alone is not that reason.

Where an applicable control is not evidenced, report that gap with a severity based on the hazard. Do not credit an unseen rescue plan or design merely because the RAMS names it. If a reading failure prevents a criterion being assessed, apply the unavailable-score rule; do not disguise a technical failure as a safety finding. If an ancillary file is not needed to reach a finding, explain that limited scope rather than assuming every missing reference invalidates the whole review.

Before accepting, the reviewer should establish how material findings are resolved: revised RAMS, additional evidence, or a reasoned disagreement tied to the activity and site. A criterion can remain applicable even where further evidence resolves its finding. Record the reviewer, date, RAMS revision, reasons and evidence relied on; preserve the original AI assessment alongside that decision and any later assessment. Keep this evidence with the review so that another competent person can understand the basis of the decision.

Acceptance does not replace required permits, briefings, checks or continuing supervision, and does not transfer statutory duties. Obtain or verify essential evidence before the affected activity starts. The contractor and principal contractor retain their respective responsibilities for implementing and monitoring safe work.

Which tests apply

A criterion that does not apply leaves the denominator and the remaining weight is renormalised, so a RAMS is neither rewarded nor punished for a test its work does not engage. That is the proportionality lever, and because it can also be a route for a real gap to disappear, version 2 puts four rules around it.

1. Eight tests always apply. Criteria 1, 2, 3, 5, 6, 7, 11 and 13 apply to every RAMS, whatever the trade: a real risk assessment, the foreseeable hazards, a stated scope, competent people and suitable equipment, task-specific hazard identification, workable controls, training and information, and monitoring. Criterion 18 also always applies whenever a requirement was issued that records an activity description; a requirement silent on the activity records no scope to conform to, so 18 does not apply with that reason. Marking any of these as does not apply is not a judgement the reviewer can make. It leaves the criterion unassessed, and the coverage rule then withholds the score. The eight weigh 50 points between them, so a scored review never rests on less than half the standard.

2. The rest apply when the activity engages them.

#CriterionDoes not apply when
4ProgrammeThe work is too short or simple for duration, sequence and hours to bear on the controls. Rare: most work engages it.
8Emergency arrangementsAn omission alone never makes this test inapplicable. Check first aid and alarm arrangements for the work, including any evidenced project arrangements; assess specialist rescue where the hazards require it.
9Temporary worksThe work described involves no temporary works and no lifting.
10Interface with others and the publicNobody other than the crew doing the work can be affected by it.
12Environmental issuesThe work produces no waste, emissions, discharge or noise that any requirement or consent governs.
14Risk category on your requirementNo hazard profile was recorded on the requirement, or the profile was rated from the submission itself.
15Legislation cited on your requirementThe requirement cites no legislation or guidance.
16Permit process you requireNo permit is required or named on the requirement, and the submission references none.
17Temporary works you referencedThe requirement references no temporary works and none are linked to it.
19Controls proportionate to the riskNo hazard profile was recorded and none can be rated from the work described.
20Organisation requirementsNo organisation requirements were issued.

The distinction that matters is between an activity that does not engage a test and a RAMS that does not evidence it. For a floor-covering installation confirmed to involve no temporary works or lifting, criterion 9 does not apply. For steel erection requiring temporary bracing, an absence of evidence for stability arrangements can be a critical failure. Judge the work and the evidence, not the trade name. Silence in the document is never a reason for does not apply.

Some of these the record decides. Criterion 16 considers the permit requirement and supplied references; criterion 17 considers temporary works referenced or linked to the requirement; criterion 20 considers issued organisation rules. Apply the record-based rules below without inventing missing project requirements. The others are judgements against the hazard profile, which is why the profile is written down first.

3. Every does not apply carries its reason. One sentence, recorded with the verdict and returned with the review, saying what about this activity takes the test out of scope: "no temporary works are involved in a floor-covering installation", not "not relevant". A does not apply with no reason counts as unassessed, and the coverage rule withholds the score rather than letting an unexplained exclusion quietly shrink the denominator.

4. Severity follows the hazard profile. The severity definitions have always been written as the consequence if the work proceeds as written. Version 2 says what that means in practice. The same finding carries a different severity on different work: missing effective rescue arrangements can be critical for confined-space entry or work relying on fall arrest. A minor documentation gap is only minor where evidenced arrangements are adequate for the actual hazards; being a ground-floor fit-out does not establish that. Consider fire, substances, access and the people affected. The factors, the caps and the band meanings do not change with the trade. What changes is which gaps are material.

Where the profile comes from. Take it from the requirement you issued. Where no requirement recorded one, a reviewer may rate the hazards from the work the submission describes, on the inherent hazard of that work and never on the document's own rating, or the RAMS under review would set the benchmark for its own controls. A profile taken from the submission cannot then be used to test it: criterion 14 does not apply, because conformity to a profile drawn from the document proves nothing, and hazard coverage is judged under criterion 2, which always applies. Where no profile is recorded and none can be rated, criteria 14 and 19 do not apply, and the review says so in those words rather than assuming a medium risk nobody assessed.

Why proportionate is the standard

Proportionality is not a softening of the review. It is what the law asks for.

Regulation 3 of MHSWR requires a suitable and sufficient assessment of the risks. What is sufficient for a carpet fit and what is sufficient for steel erection are different things, because the risks are different; an assessment that is suitable and sufficient is proportionate to the risk by construction. HSE's risk assessment guidance puts the same point plainly: you are not expected to eliminate all risks, but to do everything reasonably practicable, balancing the level of risk against the measures needed to control it.

There is no general statutory requirement for a document titled "RAMS". Risk assessment and safe planning duties still apply, and some activities require written arrangements. HSE's construction guidance identifies demolition, dismantling and structural alteration as requiring those arrangements before work begins. For many other activities, a method statement is a practical means of planning, managing and communicating safe work. A review should distinguish legal duties, recognised guidance and project requirements, and apply each to the work described.

The version 1 failure showed the cost. An adequate carpet-fitting RAMS was marked not met at major severity on temporary works, permits and referenced temporary works, because nothing told the reviewer those tests could fall away. The major-finding cap then placed it in gaps to close, next to documents with real material gaps, telling the site that work should not start until temporary works on a carpet fit were closed. Worked example 4 below runs the numbers.

The weights, factors, caps and band thresholds are shared across trades. Proportionality comes from which tests apply and how severe each gap is for the work. Equal scores do not establish equal site risk or equal review coverage: compare the applicable criteria, evidence scope, findings and rubric version as well as the number.

When software runs the review

HSE set out its regulatory approach to AI on 12 June 2026. Existing health and safety law is goal-setting, so it applies to the use of AI at work without new legislation, and the principle it applies is the familiar one: those who create risks are best placed to manage and control them "in a sensible, proportionate, and pragmatic way". Among its planned work for 2026/27, HSE lists research into cognitive offloading in AI-augmented safety decision making. (HSE's regulatory approach to artificial intelligence)

For a RAMS review that means using software changes nothing about who holds the duty. The principal contractor's review is still the principal contractor's, and the reviewer still needs to be able to read, check and overturn every verdict. This standard is built for that. The score is arithmetic, never asked of a model. Where the record settles whether a test applies, the workflow decides it and the model cannot override it. Every does not apply carries its reason on the face of the review, so the one lever that can make a gap disappear is also the one most visible to the person signing it off. A review whose exclusions cannot be read is a review that invites someone to stop reading.

The document-only subset

The twenty criteria divide by what they need in front of the reviewer, and any review claiming this standard must say which set it ran.

Criteria 1 to 13 are document-only. They assess the RAMS and any supporting evidence actually available to the review: whether the risk assessment is real and whether the method statement says enough. Together they carry 74 of the 100 weight.

Criteria 14 to 20 are comparison criteria. Every one tests the submission against something the reviewer must hold: the requirement issued for the activity (its risk category, cited legislation, permit, temporary works references, activity description and risk level) for 14 to 19, and the organisation's own rules for 20. When no requirement is held, criteria 14 to 19 do not apply; criterion 20 also does not apply when no organisation rules were issued. When a requirement exists but has blank fields, use the per-criterion rules below. Those rules allow supplied permit references for criterion 16 and an independently judged inherent hazard profile for criterion 19. They do not allow the reviewer to invent a project requirement or accept the RAMS's own residual rating as its benchmark.

What each comparison criterion compares against. So that the gates are readable on paper, and in the same words the workflow uses:

#CriterionComparison material it needsDoes not apply when
14Addresses the risk category on your requirementThe risk category recorded on the requirementNo hazard category is recorded
15Addresses the legislation cited on your requirementThe legal references cited on the requirementThe requirement records no legal references
16References the permit process you requireThe permit the requirement calls forThe requirement does not record a permit as required, names no permit type, and neither the RAMS text nor a supplied document references a permit
17Addresses the temporary works you referencedThe temporary works reference on the requirementThe requirement references no temporary works and none are linked to it
18Scope matches the activity on your requirementThe activity description on the requirementThe requirement records no activity description, so there is no scope to conform to
19Controls proportionate to the riskThe risk level recorded on the requirementNo risk level is recorded and none can be rated from the work described
20Organisation requirementsYour organisation's own compliance requirementsNo organisation requirements were issued

Where software runs the review, the workflow settles these rather than the model: "criteria 14 to 19 are not applicable when no RAMS requirement is held, with a separate basis naming each missing comparison; criterion 20 is also not applicable on a document-only run when no organisation requirements were issued. When a requirement is held, the 2.0.1 gates for criteria 14 to 18 still follow its recorded facts. An expected requirement that cannot be read stops the audit before model judgement. The model cannot override a workflow-established not-applicable verdict." A requirement that exists with blank fields is not the same thing as no requirement at all: the fields it does record are still compared.

A review run without the requirement is therefore a document-only review: at most thirteen criteria over an applicable weight of at most 74, never fewer than the eight that always apply, which weigh 50, and stated as such. It is a legitimate first pass and an incomplete review, and the result must say which it was. This is exactly how the free review at ramsreview.co.uk runs: it reads one document with no sight of any project, so it assesses the thirteen document-only criteria and reports criteria 14 to 20 as not applicable. Inside a project, all twenty criteria are considered, with applicability determined from the work and available project requirements.

Any result from a document-only review should carry the subset on its face, not in a footnote, ahead of the score: "Document-only review: 13 of 20 tests assessed, applicable weight 74" where every document-only test applied, and the actual count and weight where the activity took some of criteria 4, 8, 9, 10 and 12 out of scope. A document-only 92 and a full-review 92 are not the same level of scrutiny, and the result is the place to say so.

A result may state that coverage in plainer words on screen, provided the statement above appears on the record that goes with it. The wording is fixed for the record; the screen may say the same thing in the language of the site it is read on.

Scoring method

The score is arithmetic over the verdicts. The reviewer is never asked for a number.

Verdict factors.

VerdictFactor
Met0
Partially met0.5
Not met1.0
Does not applyremoved from denominator

Severity factors.

SeverityFactor
Critical1.0
Major0.6
Minor0.25
None0

Formula.

applicable_weight = sum of weights of criteria that apply
deduction(i)      = weight(i) x verdict_factor(i) x severity_factor(i)
score_before_caps = 100 x (applicable_weight - sum of deductions) / applicable_weight
score             = round( min(score_before_caps, cap) )

where cap = 100 when no cap condition below applies

Because no deduction can exceed its own weight, the score is inside 0 to 100 by construction.

Caps. Applied after the arithmetic, lowest cap wins.

WhenMaximum scoreWhy
Any criterion not met at critical severity49A single critical failure (no rescue plan, no temporary works design) puts the RAMS in the bottom band regardless of how much else it does well. Weighted deduction alone would leave such a submission in the nineties.
Any criterion partially met at critical severity69A partially addressed critical risk cannot sit above the significant-gaps band.
Any criterion not met or partially met at major severity89The top band is defined as "no material gaps; any findings are minor". A major finding contradicts that definition, so it must put the score below 90 however small the criterion's weight. Without this cap two major findings on low-weight criteria scored 96.

Coverage rule. Every criterion must carry a verdict. A score derived from a partial assessment is not a score: when any criterion is unassessed, report the score as unavailable and name the criteria that were missed. A does not apply with no reason, or on one of the tests that always apply, counts as unassessed.

Floor. Because the eight tests that always apply weigh 50, applicable weight is never below 50 on a scored review.

Unavailable rule. When the review could not be read or completed, the score is null with a stated reason. Zero is never used to mean "could not assess". Zero is a real score, reserved for a submission that fails every applicable criterion at critical severity.

Bands

The score is a review indicator, not a percentage of safety or legal compliance. A score of 49 may result from a critical-failure cap rather than a deduction to 49. Acceptance must address the findings and evidence, not just the band.

Band names describe the RAMS overall; they are not descriptions of the severity of individual findings. A single major finding places the whole document in the gaps-to-close band, because the top band is defined by the absence of material gaps.

ScoreBandMeaning
90 to 100No material gapsNothing material was flagged against the applicable criteria assessed within the stated review scope; any findings are minor and do not, on their own, affect safe execution.
70 to 89Gaps to closeThe substance is there, but at least one material gap remains. Work should not start until the points listed are closed.
50 to 69Significant gapsSeveral criteria are only partly addressed, or the shortfalls are wide. Expect it to come back for revision rather than be accepted as issued.
0 to 49Serious gapsThe submission has serious deficiencies, or at least one critical test has not been addressed. Send it back for rework before it goes any further.
No scoreNot scoredNot every criterion could be assessed, so no overall result is issued. The individual findings still stand.

Worked examples

1. Everything met, no organisation rules issued. Criteria 1 to 19 met; criterion 20 does not apply. Applicable weight 96, deductions 0. Score 100. No material gaps.

2. One major gap only. Everything met except emergency arrangements (criterion 8, weight 7), not met at major severity. No organisation requirements were issued, so criterion 20 does not apply. Deduction 7 x 1.0 x 0.6 = 4.2 of 96 applicable, which is 95.6 before caps. The major-finding cap brings it to 89. Gaps to close. A major gap cannot sit in the top band.

3. The steel-frame erection RAMS. A synthetic example used to design and test the method (the subcontractor and site are fictional). Twelve-storey steel frame, requirement titled "Tower crane operations, steel frame erection", citing LOLER 1998, CDM 2015 and BS 7121-1 and BS 7121-5, requiring a lifting permit and referencing the crane foundation temporary works, adjacent to an occupied office building with a noise restriction.

#VerdictSeverityDeductionPoints lost (of 100)
1MetNone00
2Partially metMajor2.702.81
3MetNone00
4Not metMajor1.801.87
5Partially metMajor1.501.56
6Not metCritical7.007.29
7Partially metMajor2.402.50
8Not metCritical7.007.29
9Not metCritical6.006.25
10Not metMajor3.003.12
11MetNone00
12Not metMajor1.801.87
13Partially metMinor0.380.39
14Not metCritical4.004.17
15Not metCritical4.004.17
16Not metMajor1.801.87
17Partially metMajor0.900.94
18Partially metMinor0.500.52
19Not metMajor2.402.50
20Does not apply

Applicable weight 96. Deductions 47.2. Score before caps 50.9. Five criteria not met at critical severity (6, 8, 9, 14, 15), so the cap applies: 49. Serious gaps. Every variable criterion is engaged by steel erection next to an occupied building, so version 2 changes nothing here. Proportionality does not rescue a document with real gaps.

4. A carpet fit, under version 1 and version 2. Also synthetic. Floor coverings on the second floor of an occupied office, adhesives in use, no temporary works, no permit, no organisation rules. The reviewer has checked applicable site first-aid, alarm and evacuation arrangements, and no specialist rescue is needed. The RAMS has a minor cross-reference omission in its emergency section: partially met, at minor severity on that evidence. Without adequate evidenced arrangements, that severity would need reassessing.

Under version 1, nothing allowed temporary works or permits to fall away, so criteria 9, 16 and 17 were marked not met at major severity. Deductions 3.6 + 1.8 + 1.8 + 0.875 = 8.1 of 96 applicable, which is 91.6 before caps. Three major findings, so the major-finding cap applies: 89. Gaps to close, with temporary works among the gaps.

Under version 2, criteria 9, 16, 17 and 20 do not apply, each with its reason: no temporary works or lifting in a floor-covering installation; no permit required, named or referenced; no temporary works referenced or linked; no organisation requirements issued. Applicable weight 84. Deduction 7 x 0.5 x 0.25 = 0.875, which is 99.0 before caps, and no cap applies: 99. No material gaps. Give the same carpet fitter a genuine major gap, such as no COSHH assessment for the adhesives, and the major-finding cap still brings it to 89, as it should.

The two scope criteria

Criteria 3 and 18 both concern scope and deliberately test different things. Criterion 3 sits in Part 2 and asks what every criterion in that part asks: is the section present, specific and adequate. Criterion 18 sits in Part 3 and does what every criterion in that part does: compares the submission with the requirement. The failures are different and so are the remedies. A vague scope means rewrite the method statement; a mismatched scope means this is the wrong RAMS for the activity. Up to v1.0.0 the two were worded so similarly that a scope mismatch was double-counted in practice; v1.1.0 corrected the wording rather than merging the criteria, so no ids, weights or scores changed.

Changelog

The published edition and machine rubric have separate versions. Edition 2.1.0 updates the guidance and checklist, including criterion 18's activity-description condition already recorded in rubric 2.0.1. It does not change criterion ids, weights, factors, caps or band thresholds, or release a new machine rubric. The previously published v2.0.0 checklist remains available. Each automated run must retain its own rubric version; publication of this edition does not retrospectively change an assessment.

VersionDateChange
2.1.0 (published edition)7 October 2026Clarified legal scope, the hierarchy of controls, supporting evidence and human decisions; qualified severity examples; reconciled comparison rules and the checklist's criterion 18 condition. Added current sources and a review-evidence record to the checklist. This is a documentation revision, not a machine-rubric release.
2.0.329 September 2026Wording only relative to 2.0.2: criteria 1, 5, 6, 9, 11, 12 and 19, including criterion 19's name, are aligned with this standard's published text. Added the per-criterion mapping of comparison material under "The document-only subset", so the gates are readable on paper in the same words the workflow uses, and recorded that a result may state its coverage in plainer words on screen provided the "Document-only review: 13 of 20 tests assessed, applicable weight 74" statement appears on the record. No ids, weights, factors, caps, band thresholds or applicability rules changed, and scores stay comparable with 2.0.2.
2.0.229 September 2026Applicability for document-only runs. Where no RAMS requirement is held, criteria 14 to 19 do not apply by deterministic gate, each with its own reason naming the missing comparison, and criterion 20 does not apply where no organisation requirements were issued. A requirement that exists, even with blank fields, keeps the 2.0.1 gates. An expected requirement that cannot be read stops the review with an unavailable reason rather than scoring around it. No ids, weights, factors, caps or band thresholds changed, and the applicable worked-example calculations are unchanged. Runs scored under 2.0.0 against an absent or partly filled requirement are not comparable with this version: absence could be scored as a document failure, contrary to this standard's own rule that a criterion whose comparison material is absent does not apply.
2.0.129 September 2026Applicability only. Criterion 18 always applies when a requirement exists and records an activity description, rather than whenever a requirement exists: a requirement with no activity description records no scope to conform to, so 18 is marked does not apply with that reason instead of the requirement's silence being scored as a document failure. The deterministic gate likewise marks criterion 15 does not apply when the requirement records no legal references, and criterion 16 when the requirement does not record a permit as required, names no permit type, and neither the RAMS text nor a supplied document references a permit. The unconditional always-applicable set, the floor of 50 applicable weight, and every weight, factor, cap, band threshold and band meaning are unchanged, and no worked example moves. Runs scored under 2.0.0 against an absent or partly filled requirement are not comparable with this version, for the same reason as 2.0.2: absence could be scored as a document failure, contrary to this standard's own rule. A re-review reports the change of scoring method on its movement line.
2.0.022 September 2026Made the review proportionate to the risk. Added the applicability rules: eight tests that always apply (1, 2, 3, 5, 6, 7, 11, 13) plus criterion 18 whenever a requirement was issued, giving a floor of 50 applicable weight; the conditions under which each other test does not apply; the distinction between an activity that does not engage a test and a RAMS that does not evidence it; a mandatory one-sentence reason for every does not apply, without which the criterion is unassessed; severity judged against the hazard profile; and the rules for a profile rated from the submission. Criterion 9 now says it is judged on the work described. Added worked example 4, the case against weighting by trade, and a section on software-run reviews. No ids, weights, verdict or severity factors, caps or band thresholds changed, and band meanings are fixed. Scores for the same document can move materially because which tests apply has changed, so this is a major version. Scores recorded under 1.x keep the version that produced them and stay readable against it; the v1.2.1 text is kept in the v1.2.1 checklist.
1.2.125 August 2026Clarified the legal and project basis in the "evidence basis" column, including jurisdiction, temporary works references, organisation requirements, environmental requirements, competent review, permits and proportionality to risk. Corrected two scoring-text examples: zero applies when every applicable criterion fails at critical severity, and example 2 now states why criterion 20 is not applicable. No ids, weights, factors, caps or band thresholds changed.
1.2.021 August 2026External review changes: corrected the 0 to 49 band description (a score below 50 can arise from accumulated major findings with no critical failure); renamed the 70 to 89 band from Minor gaps to Gaps to close and stated that band names describe the document, not individual findings; redefined minor severity as not materially affecting safe execution on its own; stated cap = 100 when no cap condition applies; reworded criteria 1 (safety-significant steps), 5 (competence evidence where applicable) and 15 (requirements addressed in method and controls); corrected the steel-frame example description from three to five critical failures. No ids, weights, factors, caps or band thresholds changed.
1.1.09 August 2026Reworded criteria 3 and 18 so the scope test each performs is distinct. No criterion ids, weights, verdict or severity factors, caps or bands changed; every score recorded under 1.0.0 remains comparable.
1.0.030 July 2026First published standard. The review score is derived from criterion verdicts rather than asked of the reviewer.

Criticism and adoption

If a weight, a test or a duty reference is wrong, tell us. Changes that alter the meaning of a stored score (renumbering, reweighting, new criteria) are published as a new major version with the old one kept readable. Clarifications are minor versions. Contributors are credited in the changelog.